Project NameWork DescriptionOperatorProject DurationDone(QTY)
I B SIBS (In Building Solution) Installation & CommissioningGrameenphone (GP)2005-20181175
I B SRepeater + Microcell Installation & CommissioningGrameenphone2007-2017843
NEW BTS/OBTSBTS Installation & CommissioningGP/Robi/Banglalink(BL)2007-20176330
NEW BTS/OBTSBTS Swap / Expansion/Supervision/TestingGrameenphone2011-20181094
NEW BTS/OBTSBTS Site Survey - New P03 ProjectGrameenphone2011-2018615
COLLOCATED BTSCollocated BTS Installation & CommissioningGP/Robi/BL2007-20181562
COLLOCATED BTSCell Addition Installation & CommissioningGP/Robi/BL20012-20183514
3G Work3G-Collocated BTS Installation & Commissioning GP/Robi/BL2010-20162600
3G Work3G-Cell Addition/Split CellGP/Robi/BL2016-2018244
TRANSMISSION WORK (MW)MW Link Installation & CommissioningGP/Robi/BL2005-20163966
TRANSMISSION WORK (MW)PDH/SDH / Space Diversity linkGP/Robi/BL2005-2016619
TRANSMISSION WORK (MW)MW Swapping with CommissioningGP/Robi/BL2008-20172293
TRANSMISSION WORK (MW)Transmission Link survey/Loss surveyGP/Robi2005-2016613
TRANSMISSION WORK (MW)PDH/SDH Hot Standby MW link InstallationGP/Robi2005-2009136
RADIO OPTIMIZATION WORKSOptimization WorksGP/Robi2005-201814793
RADIO OPTIMIZATION WORKSOptimization Project site surveyGP/Robi2007-20181045
SMALL CELLSMALL CELL Installation & CommissioningGP/Robi2014-2016336
SMALL CELL WITH DASSMALL CELL WITH DAS Installation & CommissioningGP/Robi2015-20181691
DISMANTLINGDismantling of Radio & Transmission EquipmentGP/Robi/BL2017-20163601
TX RACKTX RACK InstallationGP/Robi/BL2012-2016364
Slim RackSlim Rack InstallationGP/Robi2013-14152
BATTERYBATTERY Installation & CommissioningGP/Robi/BL2012-20171476
RectifierRectifier Installation & CommissioningGP/Robi/BL2012-2017475
hi Thi T Rack, Card, E1 Cable Installation & CommissioningGrameenphone2013-2017268
RouterRouter Installation & CommissioningGP/Robi2014-201655
Lock CascadingLock CascadingGrameenphone2014-2016399
TRX AdditionTRX Addition & DeletionGP/Robi/BL2011-20161071
Cross Connection/RoutingCross Connection/Routing/Abis/FE GP/Robi/BL2014-20182058
Traffic MigrationAoIP Traffic MigrationGP/Robi2014-20161177
TRTechnical ReviewGP/Robi2007-2017876
TMATMA Installation & CommissioningGP/Robi2007-2014278
TMBTMB Installation & CommissioningGP/Robi2007-201369
RBS/BTS SwapRBS/BTS Swapping & CommissioningGP/Robi/BL2005-2013529
HR SupplyPer Day basis HRGP2007-20178914
TRX Module ShiftingTRX Module Installation & CommissioningGP/Robi/BL201016
Pre-Commissioning Radio & Transmission Equipment Pre-CommissioningGP/Robi/BL201013
Site RectificationBTS Rectification WorkGP/Robi/BL20102
Power SupplyEricsson Site Power SupplyEricsson201049
TSSR Site SurveyTSSR Site Survey - 900Grameenphone2010-201144
TRX Add/RemovalDTRU Removal/ TRX Deletion WorkGP/Robi/BL2011109
BTS & Link DismantlingBTS & Link Dismantling Works Packing, Transportation and returned to G.P Ware House.GP/Robi/BL2005-20173558
Extension Cabinet installationExtension Cabinet Installation & CommissioningGP/Robi/BL2005-2011124
Backbone InstallationIndoor Installation at Backbone siteGrameenphone2007-2009110
GPS InstallationGPS Installation & Alarms ConnectionGrameenphone200720
Renovation WorksMinor Renovation WorksGrameenphone200715
BTS & Microwave LinkBTS (CDMA) Installation & Microwave Link installation worksGrameenphone2005-2014126
Edge PCMEdge PCM Inserting & LatchingGP/Robi2013-2018620
Traffic ShiftingE1 Traffic Shifting WorkGrameenphone2012-2013540
Re InstallationRadio & Transmission Equipment Re InstallationGP/Robi2012-2018623
MW ModificationM/W Modification Work
GP/NEC BL2012-20181049
PNMSJPNMSJ Cabling & ConfigurationGP/NEC/NEC BL2012-20181451
FE WorkFE Cabling & Configuration (IP & VLAN Config)Robi2011-2018506
Materials CarryingHand CarryRobi2017-2018119
Other WorksDC Ventilation Grameenphone20111145
Umbrella(Grameenphone)Commercial Power SiteGrameenphone2018-20172112
Umbrella(Grameenphone)Commercial Power+Diesel Generator SiteGrameenphone2018-2017504
Umbrella(Grameenphone)Non Commercial Power SiteGrameenphone2018-201782
Operation & MaintenanceCommercial Power SiteRobi/edotco2018 & Continue2480
Operation & MaintenanceCommercial Power+Diesel Generator SiteRobi/edotco2018 & Continue906
Operation & MaintenanceNon Commercial Power SiteRobi/edotco2018 & Continue127
Operation & MaintenanceCommercial Power SiteRobi/edotco2018 & Continue357
Operation & MaintenanceCommercial Power+Diesel Generator SiteRobi/edotco2018 & Continue184
Operation & MaintenanceNon Commercial Power SiteRobi/edotco2018 & Continue5